Fire & Emergency Services Station Project

Fire Station Mock-Up

Proposed Timeline

  • Currently: Formalizing TDRA Grant Extension and Finalizing Design
  • December 15, 2010 - Presentation to Board / Approval of final plans
  • January 3, 2011 - Advertise for Bids, release packet
  • January 13, 2011 - Pre-bid meeting - Council Chambers (2:00 p.m.)
  • February 3, 2011 - Bid packet due / bid opening - Council Chambers (2:00 p.m.)
  • Feb. 3 thru Feb. 15, 2011 - Scoring of bids (BRW)
  • February 16, 2011 - Scoring results to Council/Selection/Authorize CM to execute
  • Feb. 17 thru Feb. 24, 2011 - City Manager execute paperwork
  • March 1, 2011 - Issue notice to proceed
  • March 2011 - Groundbreaking Ceremony
  • March 2012 - Project Completed

(Note) - Project Updates will be a standing agenda item for every City Council meeting.